Abu Dhabi Monitoring and Control Centre ADMCC (MCC) eNOC requirement for Design and Construction NOC
Design NOC;
- Proposed work (If new provide them you design proposal)
- Assigning the corridor as per ADMCC requirements (sometimes it is with streetlighting pole or in it own corridor)
- Project Timeline.
- Auto Cad & PDF by highlighting the exact conflict location with coordinates.
- Award Letter
- Project Location
- Request Letter
Construction NOC;
- Detailed Design Approval received from AD MCC
- Proposed work Auto Cad & PDF
- If the project is not new then provide the Proposed work conflict with MCC Network highlighting the exact conflict location with coordinates (If not conflict please mentioned NO Conflict in the layout drawing).
- Kindly avoid conflict location.
- Maintain minimum 1.00 m from MCC assets.
- Concrete protection required.
- Need Conflict area cross section & Project Timeline.
- Award Letter
- Request Letter
Note: Kindly make sure to upload all your documents with adequate naming system MCC_DDMMMYYYY.zip?, where DD is current date, MMM is Month and YYYY is the year.
If in case any assistance required contact Phone No. 024058945