    TAQA Distribution requirement for Design NOC and Construction NOC

    TAQA Distribution requirement for getting Design NOC and Construction NOC fromeNOC portal.

    Two step your need to follow in Design NOC and Construction NOC stage of the project.
    1. NOI
    2. NOC
    1. NOI Requirements
      • Request letter
      • Project location Plan (pdf)
      • Award Letter/Appointment Letter
    2. NOC Requirements
      • Singed and stamped of Typical Undertaking as given with e-NOI.
      • A valid copy of NOI letter issued by ADDC Website as per link (NOI website).
      • Town Planning Sector – Abu Dhabi Municipality – planning validation approval for the works (Route Approval), Approval Letter and Approved Drawings must be attached.
      • The layout drawing showing the clear extent of works and Superimposed CAD drawing DWG file (Version 2007) in WGS84-Z40 and PDF files showing clearly the crossing/conflict of your project with ADDC Assets.
      • Letter to explain scope of works in clarity and the type of NOC (Crossing/Protection / Relocation or both of ADDC Assets). You have to clearly indicate the type/number of Crossing/Conflict Asset.
      • Detail Crossing/Protection/Relocation Method Statements for ADDC Assets including detail Cross Section in CAD drawing in WGS84-Z40 and PDF files showing clearly the clearance with ADDC assets.
      • Detailed Risk Analysis/Assessment associated with the work in all CASES.
      • For Road / landscaping Projects, Potable water / Recycled Water / Electricity Future Ducts Proposal to be submitted.
      • In case design/construction of ADDC asset as new development PDR/DDR which issued from water/electricity development departments to be uploaded.

        - For RENEWAL of any NOC, please upload same previous submittals along with new e-NOI and letter confirming that there is no changes in the scope of work and W/E Networks in project area.
    Attached Files
  • Robert Ames
    New Bees
    • Jan 2026
    • 7

    #2
    Just for you more information, If you want to get approval for Plot Expropriation then you should get eNOC APPROVAL for Plot deduction even if you submit it on MePS system.