The process of uploading attachments as outlined below:
- You must prepare all requirements related to TAQA Distribution and upload them under their designated attachment types which will get in the attachment categories:
- Electrical Zip File
- Water Zip File
- Recycled Water Zip File
- You must prepare a Shape file and labeled it as (Shape File for GHQ). Now this is done only for GHQ entity as this will only go to GHQ without being shared with any other entity as assigned in your submitted application in eNOC system.
- Lastly there is one more changes added, you need to upload the detailed Layout plan, which should include your project proposed routes, allocated service corridors, and the base map showing roads and plots within the project area and this should be uploaded in the Detailed Layout Plan options in the drop-down.
For further enquiries please contact us via noc.helpdesk@dmt.gov.ae
This source is from mail received from NOC helpdesk and this article is for educational and awareness purpose.